TI/LC Underwriting Checklist for Sponsors
Most sponsor models carry “TI/LC” as a single annual line item or a percent-of-rent placeholder. Lenders and buyers do not. They underwrite tenant acquisition cost lease-by-lease, map it to rollover timing, and then pressure-test whether reserves, escrows, and covenants can absorb the cash calls without breaking DSCR, yield-on-cost, or sale proceeds.
This checklist is built for sponsors who want lender-ready TI/LC schedules: defensible assumptions, correct timing, and reserve mechanics that match how credit committees and institutional buyers actually underwrite.
Step 1: Build a lease-level TI/LC data room (do not start in Excel)
Before you “forecast TI,” you need to know what you are contractually on the hook for. A surprising amount of TI/LC pain comes from missing lease clauses that convert “maybe” into “mandatory,” or shift timing earlier than your model assumes.
Checklist items (what to collect and normalize)
- [ ] Current rent roll with suite SF that ties to rentable area (and a reconciliation if the rent roll SF does not match BOMA or the appraisal NRA/GLA).
- [ ] Executed lease PDFs and all amendments for every tenant (including side letters). Abstracts alone are not enough for TI timing.
- [ ] Broker commission agreements (separate from leases in many portfolios). Confirm whether commissions are due at execution, at rent commencement, or in tranches.
- [ ] Tenant correspondence and default history for any tenant with renewal options coming up. Renewal probability is not a “market” input. It is tenant-specific.
- [ ] Existing TI escrow statements (if any) and lender reserve ledgers. You need to know what is already funded and what is restricted cash.
Abstract the clauses that actually move cash
You are looking for clauses that change either (a) whether you pay, (b) how much you pay, or (c) when you pay. At minimum, capture:
- [ ] Tenant improvement structure: allowance ($/SF), turnkey, “not to exceed,” landlord work letter, tenant-controlled build, landlord-controlled build, reimbursement mechanics, and what costs are eligible.
- [ ] Unused allowance treatment: forfeited, paid as rent credit, or convertible to free rent. Unused TI that converts to abatement changes effective rent and valuation.
- [ ] Renewal option language: whether landlord must fund “market TI” on renewal, whether a fixed renewal TI schedule is stated, and whether renewal rent resets to “fair market” with arbitration.
- [ ] Early termination, contraction, and expansion rights: contraction often triggers a re-tenanting capex cycle on the released space earlier than base expiration.
- [ ] Restoration obligations: who pays to remove specialty improvements at lease end. This is often modeled nowhere and hits right when you are trying to sell.
- If you cannot produce executed lease PDFs and amendments for at least 95% of in-place rent, assume you have a TI/LC gap. A buyer will haircut value or demand a holdback.
- If commission agreements are missing, assume the worst timing (due at execution) until proven otherwise. Many lenders reserve against that assumption.
- If renewal options are “at tenant’s sole discretion” and grant TI “consistent with landlord’s then-current package,” your underwriting needs a real market TI benchmark, not last year’s average.
This is also where a third-party asset management function earns its keep. Tight abstracts and variance tracking are core to lender and buyer credibility (see Third-Party Asset Management).
Step 2: Segment rollover by “renewal” vs “new deal” economics (and prove your split)
Underwriters do not accept a blended TI/LC assumption across all rollover. Renewal packages and new-deal packages behave differently across every asset class, and the differences compound because downtime, leasing velocity, and free rent usually change at the same time.
Checklist items (how to segment)
- [ ] Create a tenant-by-tenant rollover table with: tenant name, SF, base expiration, option windows, industry, credit view, sales per SF (retail), and renewal probability.
- [ ] Tag each rollover event as one of the following: “expected renewal,” “likely new deal,” “must re-tenant” (known move-out, co-tenancy risk, or non-renewing anchor).
- [ ] Assign two TI schedules: renewal TI ($/SF) and new deal TI ($/SF). Do the same for leasing commissions and free rent.
Benchmarks and why underwriters ask for them
You do not need perfect market data, but you need a defensible bracket tied to your asset quality, space condition, and competitive set. Useful published ranges can anchor the conversation, as long as you clearly treat them as context and then reconcile to your comps.
- For office underwriting, the institutional math is effective rent. A common analytical approach is to back into effective rent by amortizing TI, leasing commissions, and free rent over the lease term, then discounting. The mechanics are laid out clearly in Apers’ discussion of TI/LC, free rent, and effective rent.
- For a practical “planning range” by asset type, NextGen summarizes illustrative TI allowances by category (including office, retail, industrial, and medical office). Use it as a sanity check, then replace with your actual comp set. See Tenant improvement allowance overview and sample ranges.
Thresholds that trigger a higher TI/LC load
- Lease term under 5 years: your amortization period shortens and effective rent drops. Underwriters will often require higher yield on cost or higher face rent to compensate.
- Spec suite inventory strategy: if your plan depends on pre-building suites, you are pulling TI cash forward. That increases near-term reserve needs even if stabilized economics improve.
- Tenant-specific build complexity: medical, food, lab, and certain showroom concepts can blow through vanilla TI assumptions quickly. Treat “TI allowance” and “landlord work scope” as two separate risk items.
Do not argue that “we will negotiate tenants down.” Lenders and buyers underwrite to market clearing terms, not sponsor optimism.
Step 3: Translate lease terms into a forward TI/LC schedule with correct timing
The single biggest modeling mistake we see is correct dollars, wrong timing. Underwriting committees care about timing because timing drives: (a) peak cash need, (b) covenant compliance, and (c) whether the lender must control the disbursement process.
Checklist items (convert terms into a cash schedule)
- [ ] Map each lease event to a cash calendar: LOI, lease execution, permit start, construction start, substantial completion, rent commencement, and opening.
- [ ] Split TI into hard cost vs soft cost where possible. Even if your lender reserves against “TI,” your draw process will follow hard/soft documentation.
- [ ] Model TI as paid in draws, not a single check. A typical pattern is 30%-40% early (demo, MEP rough-in), then the balance through finishes and closeout.
- [ ] Model leasing commissions by payment trigger: execution, rent commencement, or staged payments. If your commission agreement is silent, assume earlier payment.
- [ ] Layer downtime and free rent separately. Downtime is vacancy loss. Free rent is concession during occupancy. Both reduce cash, but in different periods.
A lender-readable table structure (minimum viable output)
Your goal is a schedule that ties back to the rent roll and flows into monthly cash. Here is a structure that works in actual loan files:
| Tenant | SF | Event type | Expiration / Start | Downtime (mo) | TI ($/SF) | LC (% of base rent) | Free rent (mo) | TI timing assumption | LC timing assumption |
|---|
| Tenant A | 12,500 | Renewal | 2027-06 | 0 | 12 | 2.0% | 1 | 60% at commencement, 40% at +60 days | 100% at execution |
| Tenant B | 18,000 | New deal | 2027-11 | 6 | 55 | 5.0% | 4 | 25% at permit, 50% during build, 25% at delivery | 50% at execution, 50% at commencement |
| Tenant C | 6,200 | New deal | 2028-03 | 3 | 35 | 4.0% | 2 | Paid over 3 draws | 100% at execution |
Thresholds for “timing risk” that force reserve discussion
- If more than 20% of NRA/GLA rolls in any 12-month window, underwriters will ask for a peak cash analysis, not just annual TI/LC.
- If your TI is reimbursement-based (tenant funds then gets reimbursed), timing risk shifts to documentation and lien control. Lenders often prefer landlord-controlled draw administration.
- If your plan assumes immediate re-tenanting (zero downtime) for large blocks, expect pushback. Underwriters will haircut with downtime and carry costs unless you show executed LOIs or meaningful tenant pipeline.
If you want the TI/LC schedule to be financeable, treat it as part of capital structuring, not just leasing. This is where Capital Alignment intersects directly with asset management.
Step 4: Underwrite “effective rent,” not face rent, then tie it to value and debt capacity
Sponsors can often “win the spreadsheet” by assuming higher face rent and lower TI/LC. Buyers and lenders convert everything to an effective rent view because that is what determines sustainable NOI. The practical point is not academic: if you mis-state effective rent, you mis-state DSCR and exit cap value.
Checklist items (effective rent mechanics)
- [ ] Amortize TI over the firm lease term (not including options unless you have a real basis to include them). Options are contingent. Underwriting generally treats them separately.
- [ ] Amortize leasing commissions over the same term.
- [ ] Translate free rent into a rent abatement cost across the lease term.
- [ ] Discount or at least time-weight major concessions if your model is monthly and you are testing peak cash. Some lenders look at undiscounted cash, others look at NPV.
Apers provides a clean explanation of how TI, leasing commissions, and free rent cascade into effective rent for office underwriting, and why a face-rent pro forma can materially overstate returns and debt capacity. See effective rent cascade and illustrative ranges.
Thresholds that routinely change credit committee outcomes
- High concession load relative to term: If TI plus LC plus free rent exceeds roughly 15%-25% of total base rent dollars over the firm term (varies by asset class and market), you are in a “concessions-driven lease.” Underwriters will either haircut value or require more reserves.
- Short weighted average lease term after the business plan: If your plan increases average concessions but does not increase WALT, your NOI quality deteriorates, even if headline rents rise.
- Renewal probability mismatch: If you underwrite a 70% renewal probability but assume new-deal TI for 100% of rollover, your model is internally inconsistent. Conversely, if you assume renewals but budget new-deal downtime, your cash flow timing is wrong.
If your underwriting is debt-driven, run the TI/LC-adjusted NOI through real loan sizing tools and covenants, not just an equity IRR. A quick DSCR and proceeds check using a consistent approach helps catch issues early (see FOCAL’s Loan Calculator).
Step 5: Set lender-ready TI/LC reserves and escrows (and understand who controls the cash)
Once you have a forward schedule, the underwriting question becomes: how is this paid without creating a default? Different lenders solve this differently, but the underlying mechanics are consistent. They either (a) hold back loan proceeds, (b) require sponsor-funded escrows, (c) sweep cash flow into reserves, or (d) some combination.
Checklist items (reserve architecture)
- [ ] Decide what is “leasing capex” vs “building capex”. Many loan documents treat TI as leasing capex and draw it differently than base building work.
- [ ] Propose a reserve funding plan: at close, over time from cash flow, or upon specific triggers (rollover concentration, DSCR step-down, occupancy decline).
- [ ] Define release conditions for reserves: executed lease, lender-approved budget, lien waivers, conditional and unconditional releases, and completion verification.
Common lender patterns (what you should expect)
- Upfront TI/LC reserve sized to the next 12-24 months of known rollover costs, especially when rollover is concentrated early in the term.
- Monthly reserve deposits per occupied SF or per dollar of rent, similar in concept to replacement reserves but tied to leasing risk.
- Cash management and lockbox requirements when occupancy or DSCR is pressured. If TI/LC is large and near-term, lenders prefer control.
Even outside institutional CRE loans, the same principle appears in small business and owner-occupier contexts: fund control and draw administration exist to reduce misuse and lien risk. The CDC Small Business Finance summary of SBA 7(a) tenant improvement financing highlights that underwriting often cannot proceed without a draft lease and a walkthrough-based TI estimate, and that fund control changes contractor payment logistics. See SBA 7(a) tenant improvement funding and draw considerations.
Thresholds that justify a more conservative reserve stance
- If your TI is “landlord reimburses tenant,” assume heavier lender controls. Reimbursement structures create more fraud and lien exposure.
- If the property has meaningful small-tenant mix, commission payments can cluster unpredictably. Underwrite a commission timing buffer even if total commission dollars are accurate.
- If you are planning a near-term sale, recognize that buyers will treat unfunded TI obligations as a purchase price adjustment or a required credit.
If your loan closing checklist does not include TI/LC reserve mechanics, it is incomplete. Tie it into your broader closing workflow (see Construction Loan Closing Checklist for Sponsors, even if you are not doing ground-up. The reserve and draw logic is similar).
Step 6: Pressure-test the schedule against leasing reality and your exit
A TI/LC schedule is only as good as the leasing plan it assumes. “Market” is not a single number. It is a set of competitive constraints: tenant decision cycles, contractor lead times, permitting, and competing product delivering at the same time. Your underwriting must connect to those mechanics, then connect again to how a buyer will underwrite your exit.
Checklist items (leasing reality checks)
- [ ] Downtime by suite size and complexity: large blocks and high-build uses have longer decision and construction cycles. Model downtime as a distribution, not a single point estimate, when rollover is concentrated.
- [ ] Carry costs during downtime: utilities, cleaning, security, property tax, insurance, and leasing payroll. Underwriters will often add a vacancy OpEx load even if the building is “NNN” on paper.
- [ ] Spec suite strategy: if you plan to pre-build, treat it as a capex program with its own ROI and leasing velocity assumptions, not “TI that will happen anyway.”
- [ ] Commission rate realism: published explanations often cite 3%-6% of total lease value as a common framework depending on deal size and term. Use this as a reasonableness check, then reconcile to your market and your broker agreements. See leasing commission structures and examples.
Checklist items (exit underwriting and purchase agreement risk)
- [ ] Identify “surviving obligations” that a buyer will diligence: unfunded TI, restoration obligations, rent credits, and tenant claims.
- [ ] Normalize NOI for concessions: sophisticated buyers will underwrite effective rent and a forward-looking capex reserve. If your trailing NOI benefited from low recent leasing spend, they will adjust.
- [ ] Decide whether to pre-fund and burn off risk: sometimes the highest IRR move is to spend the TI early, lock the tenant, and remove a buyer’s holdback leverage. Sometimes it is not. You need to model both.
Decision thresholds (when you change the business plan)
- If the forward 24-month TI/LC cash need exceeds stabilized annual NOI, you do not have a “normal leasing plan.” You have a recapitalization problem unless you have committed reserves.
- If your exit cap rate sensitivity shows that a 25-50 bp move wipes out the value created by leasing, your plan is too concession-heavy for the risk you are taking.
- If your lender reserve requirements materially reduce distributable cash, revisit lease term strategy. Longer terms can improve financeability by spreading amortized concessions.
Closing: turn the checklist into a lender-ready package
A sponsor-ready TI/LC model becomes lender-ready when it is auditable. That means your schedule ties to executed documents, your assumptions are segmented (renewal vs new deal), your timing reflects real payment triggers, and your reserve plan matches how cash is actually controlled in loan documents.
The practical next step is to produce a single TI/LC underwriting exhibit that includes: (a) your rollover table, (b) a monthly cash schedule for TI, LC, downtime, and free rent, (c) your reserve proposal with sources and uses, and (d) a short memo explaining assumptions and citing where each assumption comes from (lease clause, comp, or lender requirement). If you cannot explain any single tenant’s TI cash timing in 60 seconds, you are not done.
Frequently Asked Questions
What documents do lenders expect for TI/LC underwriting?
Lenders expect an auditable lease-level package: current rent roll tied to rentable area, executed lease PDFs and all amendments, broker commission agreements, tenant correspondence for renewals, and any existing TI escrow or reserve ledgers. Abstracts alone usually miss timing and eligibility clauses.
What is the 95% lease PDF threshold, and why does it matter?
The 95% threshold means executed leases and amendments should cover at least 95% of in-place rent. Falling short signals unknown TI, commission, or restoration obligations, which often leads buyers to haircut value or require a holdback because obligations cannot be verified tenant by tenant.
When does rollover concentration trigger a peak cash analysis?
Rollover concentration becomes a timing risk when more than 20% of NRA or GLA rolls in any 12-month window. In that case, lenders typically require a monthly peak cash needs analysis for TI, commissions, downtime, and free rent, not a single annual TI/LC placeholder.
How do lenders judge whether concessions are too high?
A common credit flag is when TI plus leasing commissions plus free rent exceed about 15% to 25% of total base rent dollars over the firm lease term. That level indicates a concessions-driven lease, which can reduce effective rent, pressure DSCR, and drive higher reserves or value haircuts.
About FOCAL
FOCAL is an independent, principal-led commercial real estate investments and advisory firm headquartered in Beverly Hills, California. Through FOCAL Investments and FOCAL Advisory, the firm arranges debt and equity financing starting at $1 million for sponsors nationwide, and provides development consulting spanning land use and entitlements, owner’s representation, development advisory, and asset management.
FOCAL works across all major commercial asset classes, with deep roots in Southern California multifamily and ground-up development.
Capital Markets · Development Consulting · Closed Transactions · Contact FOCAL